Rolling Planning - Distribution#

General#

The "Distribution" sub-module of rolling planning is explained below. This planning method allows you to see the current project status and progress at a glance. At the same time, it provides an overview of the future planning process, which minimizes uncertainties in the planning. The planning can be continuously updated and an automatic distribution proposal can be used if required.

The distribution module provides an overview of the planned budgeting. You also have the option of customizing the proposed distribution in order to design the budget control of your project according to your needs.

Rolling planning can be carried out in the same way as a work breakdown structure, both on the WBS line and on the budget line.

Note

The distribution sub-module can be used independently of the forecasting sub-module, but the two complement each other perfectly.

Note

"Rolling planning (distribution)" is an activation module that can only be used with additional licensing and activation.

Setup#

Projects Setup#

Distribution#

Field Description
Distribution Active Activate the switch to use the distribution.
Invoicing Distribution Type Specifies the distribution of the billing quantity in relation to the planned quantity. You can choose from the following options:

Proportional to quantity distribution
If a quantity of 10 and a billing quantity of 20 are planned and distributed, then a 1:2 distribution takes place.

Use up the budget
There is a 1:1 distribution of quantity and billing quantity.
(Adv.) Payment in Distribution If a payment plan exists in the project, this facility is used to define whether the billing quantity in the distribution should be determined by the payment plan.
Color Planning
Color Actual
Color Distribution Suggestion
The setup fields for the colors refer to the graphs that are currently hidden.
Distribution Chart Type This field determines the graphical representation of the values in the corresponding info boxes in the quick distribution. The following display options are available:

- Line
- Bar
- Radar
Notification Planning This is used to define what should happen if over- or under-planning occurs. The following options are available:

- None
- Notification
- Error
Notification excess Capacity Planning This field can be used to control what should happen in the event of overplanning. The following options are available to you:

None
You will not receive any notification in the event of over-scheduling.

Notification
You will receive a notification in the event of overplanning.

Error
You will receive an error message in the event of overplanning. Overplanning is not possible with this option.
Default Value Distribution Finish PSP Line When a WBS line is "Closed", a default value can be defined for the purely informative field "Distribution of remaining budget", which is automatically filled when the WBS line is closed. The following selection options are available:

Retrieval
The budget can be called up for requirements at a later date.

Not required
The budget is no longer required.

Redistribution
The budget has been/will be reallocated to other PSP lines.
Update Actual Default If the switch is activated, the actual values in the distribution are automatically updated via the Codeunit for the task queue.
Commit Interval Project Queue Fill Gaps Specifies how often the changes should be committed. The default value is 500, which means that the changes are committed (written to the database) after every 500 checked project budget items.
Archive Planning If the switch is activated, the planning of the project is archived cumulatively once a month via the Codeunit for the task queue.
Hide Negative Distribution Suggestion and Invoicing If the switch is activated, it is permitted to exceed the budget and plan negatively.
Distribution Entries Filter WBS Work Status The filter is used for all actions in which the distribution is updated for several WBS rows. This allows, for example, terminated or canceled rows to be excluded in order to gain performance at the point where fewer rows are calculated and updated.
Ignore Invoice Changes on blocked Sales Budget If the billing quantity is changed in the distribution while the sales budget is blocked, an error message appears by default. The switch ensures that this message does not appear and the changes to the billing quantity in the distribution are ignored.

This only applies if the billing quantity of the distribution differs from the billing quantity of the budget line or WBS line. As long as the billing quantity remains the same, an error message does not appear, whether the switch is activated or not.
WBS Work Status Filter in Fast Distribution The filter is applied in the quick distribution view.

This makes it possible, for example, to exclude completed or canceled lines in order to obtain a better overview of the WBS lines to be distributed.
Budget Line Status Filter Fast Distribution The filter is applied in the quick distribution view.

This makes it possible, for example, to exclude completed or canceled lines in order to obtain a better overview of the budget lines to be distributed at this point.
Unit Cost Period Calculation If the cost price changes in the budget line or WBS line, this should often not affect the entire distribution. A “Fixed date” or a “Date formula” can be used to define which distribution periods should be affected.
Unit Cost Update Starting Date If the "Fixed date" option has been selected in the "Cost price period calculation" field, this field can be edited.

In this field you can enter a fixed date from which the cost price is to be changed.
Unit Cost Update Period Start If the "Date formula" option has been selected in the "Cost price period calculation" field, this field can be edited.

In this field you can enter a date formula from which calculated date (outgoing from working date) the cost price is to be changed.
Distribution Entries Period Calculation So that the distribution does not always have to check all actual postings, the date range can be limited using a fixed date or a date formula.
Distribution Entries Update Starting Date If the "Fixed date" option has been selected in the "Actual distribution item calculation" field, this field can be edited.

In this field, you can specify a fixed date from which the actual values in the distribution should be updated.
Distribution Entries Update Period Start If the "Date formula" option has been selected in the "Actual distribution item calculation" field, this field can be edited.

In this field you can enter a date formula from which date (starting from the working date) the ACTUAL values in the distribution should be updated.
Date range check actual values Specifies a date range that is to be checked beyond the ACTUAL distribution check period (previous fields).

For the check, the report "Check postings before date specification" Report 5548341 must be executed in the task queue. Only projects in which the "Check distribution of actual values" checkbox is activated are taken into account.

The lines to be checked are then visible in a tile in the Project Manager Role Center.
Update Project Queue Interval For large projects, you can specify that they should be updated via the task queue. The interval specifies how often (e.g. every 2 weeks) this update should be triggered.
Archiving Duration Specifies the duration for which an archived distribution is to be saved.
Delete Archive after Archiving Duration Specifies whether the distribution archive should be deleted after the archive duration.
Archiving Interval Specifies the time interval between archiving.
Archiving Interval Past Specifies the period of time for which archiving is to take place in the past.
Archiving Interval Future Specifies the period of time for which archiving is to take place in the future.
Warning at Deviation (Percent) Specifies a percentage deviation value for the comparison of archived schedules via the task queue. From this deviation, the value is output as defined in the "Style deviation warning" field.

Note
Please note that you can only specify one deviation value (percentage or absolute) for the warning.
Warning at Deviation (Value) Specifies an absolute deviation value for the comparison of archived plans via the task queue. From this deviation onwards, the value is output as defined in the "Style deviation warning" field.

Note
Please note that you can only specify one deviation value (percentage or absolute) for the warning.
Critical Warning at Deviation (Percent) Specifies a percentage deviation value for the comparison of archived plans via the task queue. From this deviation, the value is output as defined in the "Style crit. Deviation warning" field.

Note
Please note that you can only specify one deviation value (percentage or absolute) for the critical warning.
Crit. Warning at Deviation (Value) Specifies an absolute deviation value for the comparison of archived plans via the task queue. From this deviation, the value is output as defined in the "Style deviation warning" field.

Note
Please note that you can only specify one deviation value (percentage or absolute) for the critical warning.
Style Deviation Warning Specifies how a warning deviation is to be displayed in color (e.g. as an indicator for: Deviation must be checked).
Style Deviaition critical Warning Specifies how a critical warning deviation is to be displayed in color (e.g. as an indicator for: Deviation must be checked urgently).

Rolling Planning#

Field Description
Planning Type Default The selection of the planning type in the planning wizard is preset by default with the entry from this field. The following selection options are available:

- Budget
- PSP lines
- Mixed
Skip Planning Type Selection If this switch is activated, the selection of the planning type is not displayed in the planning wizard.
New Version Default If this switch is activated, the "New version" identifier in the planning wizard is set to "Yes" by default.
Update Distribution Default If the switch is activated, the "Update distribution" identifier in the planning wizard is set to "Yes" by default.
Distribute Difference This field defines which selection is to be preset for the "Distribute differences" field in the planning wizard.
Update Actual Default If the switch is activated, the "Update actual values" identifier is activated by default in the planning wizard.
Create New Version after Initial Planning If the switch is activated, a new WBS version is automatically created after the initial planning via the planning wizard and this is marked as the active version.
Default Page for Planning Wizard Specifies which view of the WBS is opened in the "Plan customization".
Version Selection Editable Specifies whether the WBS version may be changed in the planning wizard.
Default PSP Version for Planning Wizard This is used to specify which WBS version is opened in the "Plan adjustment" of the planning wizard.
Page Selection Editable Specifies whether the WBS view may be changed in the planning wizard.
Hide Update Distribution Specifies whether the "Update distribution" option should be hidden in the planning wizard.
Rounding Precision for Item/GL Account Specifies the number of decimal places to which the distribution for budget lines of the type "Article" and "G/L account" is rounded.
Rounding Precision for Resource/Resource Group Specifies the number of decimal places to which the distribution for budget lines of the type "Resource" and "Group" (resource) is rounded.

The other non-editable fields in the "Forecast" and "Distribution" groups show whether there are corresponding facilities. If facilities are available, this is indicated by "Yes". Clicking on "Yes" or "No" takes you to this facility. The facilities for the "Distribution" sub-module are as follows: Distribution formulas, distribution matrix work package assignment and distribution template setup are relevant.

Distribution Calc. Formulas#

You can call up the distribution formulas via a lookup using the "Distribution formulas setup" field in the "Projects setup" or via the user search.

Distribution formulas are transferred to projects and used there. If a distribution formula is subsequently changed, the "Update projects" function can be used to update the distribution formula in the projects. Only projects with the "Distribution active" indicator are updated.

Field Description
Code
Description
Formula Type
Parameter 1, 2, 3, Base Influencing the progression. You can view the exact effects of the parameters via "Open formula explanations" in the ribbon.
Start Value Here you can enter a fixed starting value with which the distribution should begin.
Use Request Page Specifies whether a query page should be opened when the distribution formula is selected, on which the parameters of the distribution formula can be changed on a line-specific basis.
Chaotic Formula Code A chaotic formula can be stored here for the "chaotic" formula.

If the "Test data (preview)" area is filled with corresponding test values, the progression of the formula can be seen in the info box.

Chaotic Formulas#

You can call up the "Chaotic formulas" via the user search.

The chaotic formulas combine several of the other formulas. To do this, the period is divided into any number of equal phases and a proportion of the total quantity is defined. A distribution formula can then be stored for each phase.

General#

Field Description
Code Specifies a code to uniquely identify the formula.
Description Specifies the description of the formula.
Status Indicates the status of the formula. Only released formulas can be used. To release, the quantity must be 100% distributed. The formula is released via "Release formula" in the ribbon.
Distributed Shows the percentage already distributed in the rows.

Lines#

Field Description
Phase No. Specifies a code to uniquely identify the phase.
Percentage Indicates the percentage share of the total quantity.
Distribution Calc. Formula Specifies the formula to be used in the phase.

Distribution Matrix Work Package Mapping#

You can call up the "Work package assignment distribution matrix" via a lookup using the "Work package assignment distribution matrix" field in the "Projects setup" or via the user search.

In this facility, the visibility of matrix row types in the distribution matrices is defined for each work package.

For example, the line types of the billing quantities etc. can be hidden for work packages that contain non-billable internal services.

This setup data is transferred to projects and used there. This means that if an allocation is subsequently changed, this change must be transferred to the projects using the "Update projects" function. Only projects with the "Distribution active" indicator are updated.

Distribution Templates#

You can call up the "Distribution templates" via a lookup using the "Distribution templates setup" field in the "Projects setup" or via the user search.

Distribution templates can be used to define a distribution in projects for each work package code. These fields are used for this purpose:

Field Description
Work Package Code Specifies the code of the work package for which the setup is to apply.
Work Package Description Specifies the description of the work package selected in the "Work package" field.
Distribution Calculation Formula Code Selection from the above distribution formulas.
Period Unit Type Specifies the period unit in which planning is to take place (week, month, quarter or year).
Distribution Level Type Specifies whether the distribution is to be made on WBS line (work package) or in the individual budget line level.
Distribution Base Type Quantity distribution (e.g. resources) or amount distribution (e.g. G/L accounts).
Distribute Differences Specifies whether the differences are to be distributed automatically.
Keep Total Quantity If "Amount" is relevant for the distribution basis, e.g. if an amount is planned with quantity 1 and this is distributed, the quantity should be 1 again after the distribution.
Use Resource Capacity Relevant when distributing quantity for resources. See application tips
No Active Planning Specifies whether there is no active planning for the line in the distribution and only the ACTUAL values are to be transferred to the planning.

Update projects#

This function can transfer subsequent changes in the "Distribution matrix work package assignment" and "Distribution formulas" settings to the projects at the same time. The update function can be executed from the two setup pages; either only one of the two or both can be updated at the same time. In general, the update only takes place in projects with the "Distribution active" indicator set.

New PSP version option values#

Setup for standard assignment of the WBS Copy report. See chapter Forecast

Project Templates#

Important parameters for new projects can already be specified on the "Lines" and "Distribution" information tabs in the project templates.

Lines#

Field Description
Distribution Calc. Formula Code Specifies the distribution formula for the row (e.g. "Linear distribution").

This specification overrides the calculation formula from the distribution formula template. Further information on the calculation formulas can be found in the section "Priority of the setup fields".
Period Unit Type Specifies the period unit in which planning is to take place (week, month, quarter or year).
Distribution Level Type Specifies whether the distribution is to be made on WBS line (work package) or in the individual budget line level.
Distribution Base Type Quantity distribution (e.g. resources) or amount distribution (e.g. G/L accounts).
Keep Total Quant If "Amount" is relevant for the distribution basis, e.g. if an amount is planned with quantity 1 and this is distributed, the quantity should be 1 again after the distribution.
Use Resource Cap Relevant when distributing quantity for resources. See application tips.
No Active Planning Specifies whether there is no active planning in the distribution for the line and only the actual values are to be transferred to the planning.
Distribute Differences Specifies whether the differences are to be distributed automatically.

Distribution#

Field Description
Distribution Active Activate the switch if the distribution is to be used for the project.
Distribution Template Code Specifies a distribution template to be used for the distribution.

This can be used to define for each work package how the individual WBS lines are later distributed over the planning period using calculation formulas (e.g. linear distribution). More on the distribution templates below.
Period Unit Type Specifies the period unit in which planning is to take place (week, month, quarter or year).
Use Distribution Setup on Lines The above-mentioned fields (Distribution active, Distribution template code, Period unit) also exist on the WBS lines and their templates; this switch defines that the distribution should only be based on these fields. This makes it possible to exclude individual WBS lines from the distribution. See also "Priority of the setup fields".
Check Distribution Actual Values Specifies whether this project should be checked to see whether there are ACTUAL postings outside the set period. Further information can be found in the section "Setting up projects - ACTUAL fields".
Archive Distribution There is a codeunit for the task queue. If the switch is activated, the planning of the project is archived cumulatively once a month via the code unit.

Work Packages#

There are also setup fields for distribution in the work package master.

Field Description
Distribution Calc. Formula Code Specifies the distribution formula for the row (e.g. "Linear distribution"). Further information on the calculation formulas can be found in the section "Priority of the setup fields".
Period Unit Type Specifies the period unit in which planning is to take place (week, month, quarter or year).
Distribution Level Type Specifies whether the distribution is to be made on WBS line (work package) or in the individual budget line level.
Distribution Base Type Quantity distribution (e.g. resources) or amount distribution (e.g. G/L accounts).
Keep Total Quantity If "Amount" is relevant for the distribution basis, e.g. if an amount is planned with quantity 1 and this is distributed, the quantity should be 1 again after the distribution.
Use Resource Capacity Relevant when distributing quantity for resources. See application tips.
Rounding Precision Specifies the rounding precision used in the distribution of budget lines for this work package to round the quantities in the planning periods.
No Active Planning Default value for the "No active planning" field in the WBS line.

Priority of the furnishing fields#

As described above, there are setup fields that can be defined in the work package master, in the WBS line and/or in the project. How these are prioritized is described below.

Distribution always takes place per WBS line. The fields of the WBS line are checked first, then the project settings and finally those of the work package master. With "Only use distribution fields of lines", the "Project" and "Work package master" levels can be deactivated so that only the setup on the WBS line is taken into account. No distribution takes place without defined fields.

User Setup#

Field Description
Edit Calc. Formulas Controls whether the calculation formulas may be changed.
Allow Edit Origin Budget Controls whether the WBS version marked as the original budget may be edited.
Allow Set Origin Budget Controls whether a PSP version may be marked as the original version.

Create project#

When creating a new project using the wizard and a project template, rolling planning fields (e.g. Active distribution) can already be checked in the wizard and adjusted for the new project if necessary. Of course, these fields can also be checked and adjusted directly on the project card on the "Planning" info tab.

Due to aggregations in the course of evaluations, it is recommended to maintain the fields "Distribution formula template" and "Period unit" in the project instead of controlling them exclusively via the WBS lines or the work package master. Ideally, these two fields should therefore already be defined in the project template.

If the WBS is also generated from the project template, the distribution setup fields contained in this template are adopted. However, these fields can be adjusted manually in each WBS line.

The "Distribution of remaining budget" field is not preset by the project template. This field determines how the remaining budget is handled when a WBS line is completed but there is still a remaining budget.

Most of the distribution setup fields are also available in the budget lines and are pre-assigned with the values from the WBS line.

The following fields are available on the WBS line and the budget line for distribution control:

Field Description
Quantity distributed Indicates the quantity that has been distributed. In the event of replanning and subsequent automatic distribution, this quantity should correspond to the budget quantity. However, if the distribution was adjusted manually, deviations may occur.
Quantity undistributed Indicates the quantity that has not yet been distributed.

In the PSP on the "Distribution" info tab, the switch with the same name is activated for an active distribution.

Distribution View#

In the ribbon of the project card, you have two distribution views analogous to the two WBS views ("Work breakdown structure" and "WBS with budget view"). The views enable a detailed view of the work breakdown structure by adding a "distribution matrix".

Distribution Matrix#

The distribution matrix is the essential element of the distribution views.

In the "WBS distribution view", the distribution matrix refers to the active WBS line. In the "WBS distribution with budget", it looks at either the active WBS or budget line, whereby budget lines are shown and hidden dynamically.

The distribution matrix shows values such as the planned quantity, broken down by planning periods, which are specified in weeks, months, etc. depending on the period unit. Which rows are visible in the matrix depends on the settings in the "Work package allocation distribution matrix".

The information contained in the individual rows of this matrix is essentially self-explanatory or will be discussed in more detail later. Therefore, only the following will be explained in more detail here:

Field Description
Planning line The top line is used for the actual planning and shows the current distribution values. It also contains descriptive texts from the budget or WBS line that are the subject of the planning. The values within the matrix are created by distribution items and can be adjusted manually. These adjusted values are later transferred to the project budget as project budget items.
Distribution proposal Proposal for new planning created via the function. These values are also created with specially filtered distribution items. These values cannot be changed manually. This proposal can be transferred to the planning line via a function.
Ist The actual values from the project items can be updated for each planning period using a function.

Function Distribution Matrix#

In the distribution matrix, the following three functions should be used one after the other and in this order:

  1. update actual values
  2. transfer actual/distribution proposal to planning
  3. update order backlog

The "Update distribution" function combines these tasks and executes them automatically in the correct order with a single call.

Update actual values#

The actual values shown in the matrix are updated based on the project items. Unused residual budget is automatically distributed to the next periods, which means that completed activity periods no longer contain any quantities in the distribution proposal.

See also Sequence of an update after completion of a performance period.

Transfer Distribution suggestion in Planning#

Once the distribution proposal has been incorporated into the planning, the planned billing quantities can be updated on the basis of the new planning.

See also "Sequence of an update after completion of a performance period".

Note

A distribution to the current period does not take place; it only takes place in the following periods.

Update Invoicing#

Once the distribution proposal has been incorporated into the planning, the planned billing quantities can be updated on the basis of the new planning.

See also "Sequence of an update after completion of a performance period".

Update Distribution#

Combines the three functions described above in a single call. This function automatically executes all three functions one after the other.

Reset Planning#

A manual distribution can be automatically redistributed using the "Reset planning" function on the basis of the distribution settings; the manual changes are lost in the process.

Distribution#

Planning quantity#

If a new budget line is created on the "WBS distribution with budget view" distribution page and the start and end date are specified, the budget quantity entered is automatically distributed in the distribution budget matrix based on the selected distribution setup. For example, from 01.11. to 30.06. there is a monthly linear distribution by quantity.

The top line in the distribution matrix (budget line description) shows the current planned quantity, which corresponds to the distribution proposal line after automatic distribution. If necessary, the planning can be changed manually in the first row, while the values in the distribution proposal row remain unchanged.

Planning amount#

Distribution by amount also automatically takes the setup fields into account and distributes the planning automatically as soon as all the data has been entered. In contrast to quantity distribution, however, the distribution here is based on the amount. A typical example of this is costs that are assigned to a G/L account with a quantity of 1 and a cost price in the budget line. In this case, it is not the quantity 1 that is distributed over the periods, but the amount. If the setting provides for the total quantity to be retained, the quantity is divided up, taking into account the rounding precision, so that the sum of the distribution items is again quantity 1. It is not the quantity that is relevant here, but the amount.

Automatic Update#

If planning-relevant fields such as "Cost price" or "Start date" are changed, the distribution can be updated automatically after consultation.

Distribution Entries#

The distribution items are parallel to the project budget items. Budgeting can be generated from these distribution items, making them the first planning stage from which the project budget items later emerge. The distribution items can be viewed, for example, using a lookup in the "Quantity distributed" field.

Distribution entries transfer value#

This function takes over a distribution in project budgeting by synchronizing the distribution items with the project budget items. Existing budget items are replaced in the process. With this transfer, the application closes the loop to the range of functions explained in the "Project planning" section.

Distribution transfer value#

There are two versions of this function, one for the current PSP line and one for all PSP lines. All planning levels are updated.

The distribution items of the budget lines update the budget items and thus the planning in the budget lines. The planned values are transferred from the budget lines to the corresponding WBS line.

Workflow#

Distribution in project budget lines#

(Initial planning according to bottom-up method)

Distribution level is the budget line

  1. create budget lines with planning-relevant fields, especially the planned quantities
  2. a distribution proposal is created.
  3. transfer of the distribution proposal with the function "Transfer distribution proposal to planning"
  4. possible manual change of the planning (= distribution)
  5. transfer of the distribution quantity as new planned quantities in the budget lines with the function "Update values from distribution items"
  6. transfer of the planning from the budget lines to the WBS lines.

Some of these functions can be executed automatically one after the other.

Distribution in WBS Lines#

(Initial planning according to top-down method)

Distribution level is the WBS line

  1. rough planning takes place on the WBS line
  2. a distribution proposal is created
  3. detailed planning (if desired)

Sequence of update after completion of performance period#

An example will illustrate this update. In a budget line, 600 hours are distributed linearly over 6 months. The start month is January, the end month is June. In the initial planning, a distribution was created and transferred to the budgeting that contains the following values:

Jan 100
Feb 80
March 120
April 80
May 120
Jun 100

In January, 80 hours are booked (i.e. 20 less than planned). We are now in February. January will be completed and the planning will be updated.

With the "Update actual values" function, the 80 hours of actual values are transferred to the distribution matrix and a new distribution proposal is created at the same time, which takes into account the completed month of January with 0 and distributes the 20 hours not worked over the remaining months.

Vert. Vorschl. Ist
Jan 80
Feb 85
March 122
April 85
May 125
Jun 103

The distribution proposal can now be transferred to planning using the "Transfer distribution proposal to planning" function. However, the new planning has not yet arrived in the project budget items. The planning can still be changed manually.

The "Update order backlog" function is used to adjust the planned billing quantities to the new planning.

The budget line function "Update values from distribution items" can now be used to update the project budget items from the new distribution items.